Aug 25th - Sep 08th
Executive Summary
Overall Status
The Product team prioritized the following themes and tasks for Sprint 139 comprising 24 points. These themes included -
- Partner and Community support
- Forum discussions
- Community and OHT support
- SSA 4.3.2 implementation
- Continued 4.3.2 RC1 Testing/ Monitoring
- VA 4.2.2.1 implementation
- Partner Questions
- Community support with certification testing
- X12 (Synchronous Testing, Generic Batch Dev, Update and Finalize Design Approach)
- SSA & VA Implementation Support
- Healtheway Product Certification Support (Research and Support for Vendor Reported Issues, Wiki Page Updates)
- Admin GUI (Password and Multiple Call Bugs)
Sprint status is excellent and the team completed 26 points this sprint, one ticket that was pulled in to fix an issue related to content type header missing semicolon, that was resulting in an interoperability issue with partner integration at VA.
Release 4.2.2.2 was made available to the community this sprint. The team completed the X12 Document Submission framework for the deferred/generic batch submission time transactions.
Burndown