Aug 25th - Sep 08th
Executive Summary
Overall Status
The Product team prioritized the following themes and tasks for Sprint 139 comprising 24 points. These themes included -
- Partner and Community support
- X12 (Synchronous Testing, Generic Batch Dev, Update and Finalize Design Approach)
- SSA & VA Implementation Support
- Healtheway Product Certification Support (Research and Support for Vendor Reported Issues, Wiki Page Updates)
- Admin GUI (Password and Multiple Call Bugs)
Sprint status is excellent and the team completed 26 points this sprint, one ticket that was pulled in to fix an issue related to content type header missing semicolon, that was resulting in an interoperability issue with partner integration at VA.
Release 4.2.2.2 was made available to the community this sprint. The team completed the X12 Document Submission framework for the deferred/generic batch submission time transactions.
Burndown
Sprint Themes and related tickets for Sprint 139:
Community Implementation support
- Forum discussions
- Community and OHT support
- SSA 4.3.2 implementation
- Continued 4.3.2 RC1 Testing/ Monitoring
- VA 4.2.2.2 implementation
- 4.2.2.2 was released with some bug fixes - /wiki/spaces/CONNECT4/pages/10584084
- Fixes include
- Missing semi-colon in content-type header (CONN-1321)
Merlin Crypto package classes read their related properties files from the bundled Properties.jar library; not the "config/nhin" folder(CONN-1178)
Modify logging/exception detail for troubleshooting endpoint exceptions(CONN-1184)
NwHIN PD response can have invalid creation time(CONN-1114)
- Partner Questions
- Community support with certification testing
Support and research Healtheway product certification issues
Next Release (4.4)
- Admin GUI
- Fixed issues related to inconsistent UI field sizes on Admin GUI screens (CONN-1254)
- Support for NwHIN CAQH Core X12 Document submission service
- Team reviewed the progress made last sprint with CMS team
- CONNECT team demonstrated the work done so far on the Real time/synchronous service for X12 Document submission.
- Completed Real Time request and response framework
- Created X12 RealTime reference adapter to simulate response to a RealTimeRequest.(CONN-1281)
- Created RealTime Transaction Test Case and added it to the ConnectValidation Test Suite.(CONN-1282)
- Created X12 profile and packaged X12 modules in the CONNECT EAR.(CONN-1285)
- Design approach draft created and updated on the wiki
- Started work on creating Generic Batch submission projects and framework (CONN-1299,CONN-1298, CONN-1309)
- Team reviewed the progress made last sprint with CMS team
JIRA Planning Board of Committed User Stories for Sprint 138: