February 9th - February 23rd
Executive Summary
Overall Summary
The team will be focusing on the following themes during Sprint 151
- Partner and Community support
– Forum discussions
– Support for the Federal Agencies
– Community support - X12 Audit Research and Design
– Meet with CMS to finalize Auditing requirements
– Complete requirements and design - Gateway Properties Refinement and Demonstration
– Finish gateway properties research and wrap up design
– Complete proof-of-concept and demo readiness - Technical Stories
– Test Direct poller setup
– CXF unbundling/Proxy timeout
– Encryption of stored Direct Certificate
– Testing improvements, automation and cleanup