April 20th - May 4th
Summary
Sprint status is excellent. The Product Team had prioritized the following themes and tasks for Sprint 156 comprising 13 points -
The CONNECT Product will be focusing on the following themes for Sprint 156:
- HIMSS 2015 Interoperability Showcase Demonstration
- Finish up Document Submission for complete suite of adapters
- Work on plug-in approach to provide to the community
- X12 Auditing Development, Integration and Testing
- Complete creation of testing artifacts
- Technical Stories
- Direct testing automation
- Further follow-up on SAML assertion prefix issue
The team pulled in additional tickets related to Direct test automation and completed 19 points this sprint.
Burndown:
Sprint Themes and related tickets for Sprint 156:
Partner and Community Support
- The team continued to support the community via the CONNECT forums.
- The team followed up on the CMS related to SAML assertion ID parameter.
- CONNECT is sending a compliant message per the specification, specficication information and CONNECT behavior was explained to implementation team.
- Requested follow-up on workflow and how Assertion ids are being sent over to the gateway.
CONNECT Development
- Completed creation of a Fusion FHIR adapter for Document Submission, that is able to successfully submit a document from requesting gateway to the responding gateway (with a FHIR server backend).
- Was able to test the functionality by retrieving the document using the Universal Client..
- Worked on creating regression (automated) testing artifacts for Direct functionality
- Direct automated test cases for inbound Direct messages are completed - \CONNECT\Product\SoapUI_Test\RegressionSuite\Direct
- Completed creating testing artifacts for X12 audit logging for Real Time and Generic Batch transactions(Pass through mode)
JIRA Planning Board of Committed User Stories for Sprint 156:
Related Files for Sprint 156:
Sprint 156 code tag
Common-Types source
CONNECT-Webservices source