May 19 - June 2, 2014

 

Executive Summary

Overall Status

Sprint status is fine. The Product team prioritized the following themes and tasks for Sprint 132 comprising 28 points. These themes included - 

  • Community support (VA 4.2.1, OHT, Forums)
  • Continue new feature development for Admin GUI with Role based access, Framework finalization, demo preparation 
  • Continue new feature development for Direct  enhancements to include testing Trust Bundles and creating test artifiacts, participating in Direct Connect-a-thon, investigating multi- application support.
  • Research and requirements gathering for CMS/X12 support.
  • Healtheway Product certification test cases review.

The team pulled in a few tickets this sprint as the team was blocked on some of the Direct related tickets. 

The team completed XX points this sprint. XX ticket(XX points) was not completed and will be moved over to the next sprint.

Burndown

 

Sprint Themes and related tickets for Sprint 132:

 

JIRA Planning Board of Committed User Stories for Sprint 132: