Jun 16 - June 30, 2014
Executive Summary
Overall Status
The Product team prioritized the following themes and tasks for Sprint 134 comprising 34 points. Sprint status is fine and the team completed all the tasks for the themes this sprint . These themes included -
THEME 1 – Complete Direct development from a Config services integration on all app servers and implementing the base framework for message monitoring
THEME 2- Complete consolidating look and feel for all Admin GUI pages including Direct Config GUI
THEME 3 – Continue to work with CMS to come to a common understanding of what will be delivered and understand clearly the expectations
In addition to the rest of the themes described above the Product Team will continue its support of the community(Tiani/INHS), ongoing support for VA on their 4.2.1 upgrade, work with OHT and Healtheway product certification testing.
The team completed 18 task oriented tickets totaling 34 points this sprint.
Burndown
Sprint Themes and related tickets for Sprint 134:
- Community Implementation support
- Responded to forum posts - http://www.connectopensource.org/developer-resources/forums
- Support VA with 4.2.1 upgrade (CONN-1174,CONN-1179)
- Continued discussions with VA as they work on the 4.2.1 upgrade. Fixed an issue in
- Provided information to the VA implementation team on implementing fan-out with standard mode of the gateway and discussed considerations for the same.
- /wiki/spaces/CONNECTWIKI/pages/17825814
- Continued discussion with CMS on X12 support and understanding requirements (CONN-1173)
- Participated in the CMS JAD.
- Presentation can be found here -https://connectopensource.atlassian.net/wiki/download/attachments/10190953/CONNECT%20X12.pptx?version=1&modificationDate=1403870671608&api=v2
- Meeting notes can be found here - https://connectopensource.atlassian.net/wiki/download/attachments/10190953/Meeting%20Notes_CMS%20JAD%20June%2023%202014.docx?version=1&modificationDate=1403870645626&api=v2
- Updated requirements page - Support for X12 messaging(Draft)
- Draft story plan for 278 to discuss our understanding with CMS - 278 Story Plan(Draft)
- Need further discussion on WSDL definitions - See wiki page /wiki/spaces/CONNECTWIKI/pages/17203353
- Participated in the CMS JAD.
- Follow-up with Tiani/INHS with timestamp/signature validation (CONN-1177)
- Next Release (4.4)
- Direct enhancements
- Converted CONNECTDirectConfig to use HIbernate for database access(CONN-1161, CONN-1139)
- Created test artifacts for Direct test cases using Trust Bundles (CONN-1113)
- Updated Direct design to include message monitoring(CONN-1088)
- Tested Direct config services on all application servers (CONN-729)
- Validated that it works on GlassFish, WebSphere and JBoss.
- Identified a known issue with Auto refresh implementation using camel and will be addressed later.
- CONN-1188 will be addressed later, added to backlog
- Deployment issues were discovered with WebLogic (will be addressed next sprint including retesting on all app servers)
- Admin GUI feature
- Updated all current PrimeFaces pages with the correct CSS for look and feel including Direct Config GUI pages(CONN-1142 and CONN-1151 and supporting tasks)
- Migrated all Direct Config GUI wireframes to PrimeFaces (CONN-1118)
- Bug fixes
- Updated test script for PurposeOfUse value in the validation suite to use a supported value.(CONN-1171)
- Direct enhancements
JIRA Planning Board of Committed User Stories for Sprint 133:
Related Files
Sprint 134 code tag