Executive Summary
Overall Status
Sprint status is Excellent. The team accomplished all of the thematic work defined for the sprint and the release.
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 113 comprising 24.5 points.
Proposed Themes:
- Rerun all Release 4.2 Testing on new GA build
- Installation testing
- Validation testing
- Interoperability testing
- Complete Release 4.2 Documentation
- Continue working with Healtheway/ CCHIT on certification program readiness
- Discussing and addressing final items from updated certification test cases
- Final release preparation tasks for Release 4.2 availability
- Next steps in CI and testing automation improvements
Prioritized JIRA Planning Board of Committed User Stories for Sprint 113
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
Related Files
- Sprint 113 review notes\ - Notes about the work completed in s113. (Also includes work planned for s114)
- Sprint 113 planning notes - Notes about the work planned in s113. (Also includes work completed in s112)
- JIRA. See Sprint 113
- Release 4.2 code tag