May 19 - June 2, 2014

Executive Summary

Overall Status

Sprint status is fine, but the team was not able to accomplish all the tasks for the sprint. The Product team prioritized the following themes and tasks for Sprint 132 comprising 28 points. These themes included - 

  • Community support (VA 4.2.1, OHT, Forums)
  • Continue new feature development for Admin GUI with Role based access, Framework finalization, demo preparation 
  • Continue new feature development for Direct  enhancements to include testing Trust Bundles and creating test artifiacts, participating in Direct Connect-a-thon, investigating multi- application support.
  • Research and requirements gathering for CMS/X12 support.

The team pulled in a few tickets(6) this sprint as the team was blocked on some of the Direct related tickets. 

The team completed 11 tickets totaling 25 points this sprint. 7 tickets(14 points) was not completed and will be moved over to the next sprint.

Burndown

Sprint Themes and related tickets for Sprint 132:

  • Community Implementation support
  • Next Release (4.4)
    • New Features for next release
      • Participated in the Direct connect-a-thon and tested the trust bundles integration capability.(CONN-1110)
        • Were able to successfully communicate bidirectionally with 8 of the 14 HISPs participating in the Direct Connect-A-Thon.
        • New tickets created for investigation with some testing vendors where the communication failed e.g. Subject Alt Name in certificate missing, Content Type Mismatch error, Errors when Multiple recipients etc. (see CONN-110 for details)
      • Administrative GUI enhancements 
        • Included role based access to restrict access based on functionality (CONN-1111)
        • Display total inbound and outbound transactions for Direct service (CONN-1119)
        • Fixed register Direct event to store service type and community ID(CONN-1134)
        • Added CONNECT logo on Admin GUI pages and other GUI improvements(CONN-1123/CONN-1140)
        • Migrate wire frames to Prime Faces for Admin GUI/Create User display.(CONN-1125)
        • Created an Admin GUI User manual page for Administrative GUI functionality in CONNECT(CONN-1133)
      • Bug fixes and other improvements this sprint
  • Ongoing Custodial Agent Duties
    • CONNECT 4 Blogs and Forum posts

JIRA Planning Board of Committed User Stories for Sprint 132:


Related Files

Sprint 132 code tag