April 22th - May 5th, 2013

Executive Summary

Overall Status

Info

Sprint status was excellent. The team accomplished almost all of the thematic work defined for the sprint.

Burndown

Image Added

Cumulative Flow

Image Added

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 106 comprising 11 points.

...

  • Continued Testing for Java 6 & Java 7 Support
    • Installation testing on WAS 7 /IBM SDK 1.6
    • Installation testing on WL 11g / JDK 1.6
    • Installation testing on WL 12c / JDK 1.7
    • Installation testing on WAS 8.5 /IBM SDK 1.7
    • Installation testing on JBoss 7.1.1 /JDK 1.7
    • Installation testing on GlassFish 3.1.2 /JDK 1.7
    • Smoke test on all installations
  • Research and Write Design Approach for Multi-Specification Identification for QD/RD (Initiating)
    • Review design approach with technical leads from Federal Partners (conference call)
  • HealtheWay certification pilot testing (system set up and smoke tests)

Prioritized JIRA Planning Board of Committed User Stories for Sprint

...

106 