Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

Sprint Review + Planning | April 22th | 10am - 12pm ET

Registration for webinar: Click link below to register, and receive dial-in and Web participation details: 

https://attendee.gotowebinar.com/register/7556627107749161728

April 22th - May 5th, 2013

Executive Summary

Overall Status

Sprint status was excellent. The team accomplished almost all of the thematic work defined for the sprint.

Burndown

Cumulative Flow

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 106 comprising 11 points.

Proposed Themes:

  • Continued Testing for Java 6 & Java 7 Support
    • Installation testing on WAS 7 /IBM SDK 1.6
    • Installation testing on WL 11g / JDK 1.6
    • Installation testing on WL 12c / JDK 1.7
    • Installation testing on WAS 8.5 /IBM SDK 1.7
    • Installation testing on JBoss 7.1.1 /JDK 1.7
    • Installation testing on GlassFish 3.1.2 /JDK 1.7
    • Smoke test on all installations
  • Research and Write Design Approach for Multi-Specification Identification for QD/RD (Initiating)
    • Review design approach with technical leads from Federal Partners (conference call)
  • HealtheWay certification pilot testing (system set up and smoke tests)

Prioritized JIRA Planning Board of Committed User Stories for Sprint 106 

Related Files

  • No labels