Nov 3rd - November 17th
Executive Summary
Current Status
The Product Team has prioritized the following themes and tasks for Sprint 144 comprising 42 points. These themes included -
- Release 4.4 Preparation
- Development (Any testing defects, logging issues, WAS issue)
- Test Prep (Interop setup, script updates)
- Testing (Further end to end testing of Admin GUI & X12, NIST, EHEX)
- Documentation (Continue with Release 4.4 required documentation tickets)
- Close completed Release 4.4 User Stories (Direct, Admin GUI, Direct)
- Create Release Candidate 1 Binaries
- Prep for Nov. 13th Partner Release 4.4 Demonstration
- Support for the Federal Agencies Implementations (VA, CMS, DoD, SSA)
- Support any CMS X12 Testing Activities