Sprint Review + Planning | April 22th | 10am - 12pm ET
Registration for webinar: Click link below to register, and receive dial-in and Web participation details:
https://attendee.gotowebinar.com/register/7556627107749161728
April 22th - May 5th, 2013
Executive Summary
Overall Status
Sprint status was excellent. The team accomplished all of the thematic work defined for the sprint.
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 106 comprising 11 points. The team added 2.5 points to the sprint with a total of 13.5 points. The team completed 13 points
- Continued Testing for Java 6 & Java 7 Support
- Installation testing on WL 11g / JDK 1.6 (CONN-383/CONN-384)
- Installation testing on WL 12c / JDK 1.7 (CONN-371)
- Installation testing on WAS 8.5 /IBM SDK 1.7 (CONN-370)
- Installation testing on JBoss 7.1.1 /JDK 1.7 (CONN-368)
- Installation testing on GlassFish 3.1.2 /JDK 1.7 (CONN-369)
- Smoke test on all installations
- Documentation (CONN-375)
- Research and Write Design Approach for Multi-Specification Identification for QD/RD (Initiating)
- Review Responding design approach with technical leads from Federal Partners (conference call)
- Initiating design approach -
- HealtheWay certification pilot testing (system set up and smoke tests)
- CONN-317 Pre-test and smoke test for pilot https://developer.connectopensource.org/display/CONNECTWIKI/Table+1+-+Test+Cases+%28subset%29
JIRA Planning Board for Sprint 106
Related Files
- Sprint 106 review notes\- Notes about the work completed in s106. (Also includes work planned for s107)
- Sprint 106 planning notes - Notes about the work planned in s106. (Also includes work completed for s105)
- Sprint 106 code tag
- JIRA. See Sprint 106